Skip to the content
Phone: 0416 337 597
Email: kynan@davisweldandfab.com.au
Services
Contact
logo mainlogo darklogo light
  • HOME
  • ABOUT
  • SERVICES
    • Welding and Fabrication Brisbane
    • Commercial Welding
    • Food and Beverage Processors
    • Commercial Boilermaker Services
    • Galvanized Steel Concrete Reinforcements
  • PROJECTS
  • BLOG
  • CONTACT
logo main
  • HOME
  • ABOUT
  • SERVICES
    • Welding and Fabrication Brisbane
    • Commercial Welding
    • Food and Beverage Processors
    • Commercial Boilermaker Services
    • Galvanized Steel Concrete Reinforcements
  • PROJECTS
  • BLOG
  • CONTACT
logo main
  • HOME
  • ABOUT
  • SERVICES
    • Welding and Fabrication Brisbane
    • Commercial Welding
    • Food and Beverage Processors
    • Commercial Boilermaker Services
    • Galvanized Steel Concrete Reinforcements
  • PROJECTS
  • BLOG
  • CONTACT
HomeProject 2Stainless-steel CO2 vent pipe fabrication

Stainless-steel CO2 vent pipe fabrication

Client:

Green Beacon Brewery, Geebung

 

Project description:

Stainless-steel CO2 vent pipe fabrication

Design, fabricate and install a stainless-steel CO2 vent pipe. This pipe was needed to vent CO2 formed in the brewing process safely outside the building, so it didn’t accumulate inside the facility causing a possible safety risk to employees.

 

What were the challenges?

  • The brewery has many tanks and associated equipment located in a small facility. Space was very restrictive.
  • The CO2 pipe needed four inlets spaced accordingly around the brewing tanks.
  • The pipe then needed to exit through the roof of the building.

 

How did Davis Welding and Fabrication solve these challenges?  

  • A site visit was conducted to ensure all requirements were clearly understood by our team.
  • Measurements were taken of how we could fit the pipe amongst the existing equipment.
  • A proposed design was submitted and discussed with the client
  • Once approved the pipe was 95% manufactured offsite in our workshop
  • To ensure resistance to corrosion and to abide by the highest hygiene standards 316 grade stainless steel was used and all joints in the pipe were purge welded.
  • To fit in with the client’s production schedule the install was planned outside their operating hours on a Saturday.

 

Project result:

  • The pipe was fully functional for the following Monday’s production as requested.
  • The pipe fitted perfectly as planned, only minor welding was carried out onsite to install some brackets to support the pipe.
  • The addition of this pipe has eliminated a large safety risk within the client’s production process.

 

Category:
Project 2
Date:

April 12, 2023

Share:
Galvanised Maintenance Platform Prev Spray Cabinet Fabrication Next

Davis Welding & Fabrication

Design, manufacture, and installation of specialist commercial metal fabrications and solutions. Servicing Brisbane, Gold Coast, and inner Southeast Queensland.

Quick Links
  • HOME
  • ABOUT
  • SERVICES
    • Galvanized Steel Concrete Reinforcements
  • PROJECTS
  • CONTACT
  • Privacy Policy
  • Terms of Service
Email

kynan@davisweldandfab.com.au

Phone

0416 337 597

Copyright © 2025 Davis Welding & Fabrication, all rights reserved | Website by Success Marketing

TALK TO US ABOUT
YOUR PROJECT

OFFICE HOURS

Office hours: 5:00am – 2:00pm
Hours of service operations: 7 days a week as required.

LOCATION

26 Horizon Drive,
Beenleigh QLD 4207

EMAIL

kynan@davisweldandfab.com.au

PHONE

0416 337 597